Millstone Subdivision Progress as of October 17, 2016
- South Sawmill Road has been repaved.
- All underground utilities have been completed in Section II.
- Lime stabilization for the streets will begin on October 18, 2016 (may cause dust in the air).
- Curbs and paving will follow in the next couple of weeks.
- Arbor Homes is now selling lots for Spring delivery of new homes.
- Section III earth moving will get underway after crop harvest.
- Pond excavation will also be finishied after the crop harvest.
The Millstone Subdivision project is on schedule.